Przeplanowanie
Observatory

Production Disruption Decision

Battery recycling · Production replanning demonstrator

Synthetic demonstration — not BTS & SAKER production data

Production disruption
At risk

Line A:

80 → 56 t/day

Capacity reduction

−30%

Capacity lost over disruption

72 t

Remaining capacity (disruption period)

168 t

Duration

3 days

Recommended action

REDISTRIBUTE PRODUCTION

Recommended
74% score

Estimated impact

€70.700

vs. keep current plan

€97.671

Potential avoided cost

€26.971

Critical deadlines

Protected

Synthetic demonstration values

Why this recommendation?

Critical deadline protected

Critical order(s) can complete by day 0.9 (deadline: day 2).

Disruption adequately compensated

REDISTRIBUTE_PRODUCTION compensates for the 3-day disruption, during which Line A operates at 70% of normal capacity (−30% reduction).

Lower total financial impact

Saves €26,971 compared to keeping the current plan.

Rejected alternatives

DELAY LOW PRIORITY ORDERHigher total cost — €11,200 more than recommended action.
PRIORITIZE CRITICAL ORDERHigher total cost — €14,800 more than recommended action.
KEEP CURRENT PLANINFEASIBLE — Critical order(s) estimated completion day 2.1 exceeds deadline day 2.

Current plan vs. recommended plan

Current planRecommended
Critical deadlinesAt riskProtected
Capacity utilisation17%17%
Tonnes processed270 t270 t
Financial impact
Missed deadline cost€20.571€0
Overtime cost€0€0
Delay cost€9.600€0
Unused capacity cost€67.500€67.500
Switching/reconfiguration cost€0€3.200

TOTAL€97.671€70.700
AVOIDED COST€26.971

Production plan — per line

Current plan

Line A56 t/day

Order A120 tday 2.1 ⚠ LATE
Order B90 tday 3.8

Line B55 t/day

Order C60 tday 1.1

Recommended plan

Line A56 t/day

Order A51 tday 0.9
Order B38 tday 1.6
Order C26 tday 2.1

Line B55 t/day

Order A50 tday 0.9
Order B38 tday 1.6
Order C25 tday 2.1

Change scenario

Adjust any parameter — the decision engine recalculates immediately.

0–60%

1–10 days

50–600 t

1–14 days

All alternatives — ranked

#1Redistribute production
FEASIBLE
74% score
€70.700
#2Delay low-priority order
FEASIBLE
71% score
€81.900
#3Prioritise critical order
FEASIBLE
70% score
€85.500
#4Keep current plan
INFEASIBLE
9% score
€97.671

Decisive factors

Critical deadline protected

Critical order(s) can complete by day 0.9 (deadline: day 2).

Disruption adequately compensated

REDISTRIBUTE_PRODUCTION compensates for the 3-day disruption, during which Line A operates at 70% of normal capacity (−30% reduction).

Lower total financial impact

Saves €26,971 compared to keeping the current plan.

Rules catalogue

RULE-CAPACITY
Capacity feasibility
blocking

The proposed plan must fit within available production capacity.

RULE-MATERIAL
Material availability
blocking

Sufficient feedstock must be available to execute the plan.

RULE-CRITICAL-DEADLINE
Critical deadline protection
blocking

The plan must not miss the deadline for any CRITICAL order.

RULE-PRIORITY
Priority ordering

Higher-priority orders should be scheduled before lower-priority ones.

RULE-UTILIZATION
Capacity utilisation

The plan should use available capacity efficiently.

RULE-DISRUPTION
Disruption compensation

The alternative must adequately compensate for the production disruption.

RULE-COST
Financial consequence

The estimated total cost of the alternative must be evaluated.

Cost assumptions

All values are synthetic demonstration assumptions. Not BTS & SAKER figures.

Missed CRITICAL deadline€1.200 / t·day
Missed HIGH deadline€400 / t·day
Overtime premium€180 / t
Production delay (NORMAL)€80 / t·day
Unused capacity opportunity cost€50 / t/day · day
Material handling / line switching€3.200 (one-time)

Audit trail

Decision ID: PRD-BTS-DEMO-001-WHATIF-1.0.0

Scenario ID: BTS-DEMO-001-WHATIF

Engine version: 1.0.0

Config version: 1.0

Computed at: 2026-01-15T09:00:00.000Z

Alternatives evaluated: KEEP_CURRENT_PLAN, PRIORITIZE_CRITICAL_ORDER, REDISTRIBUTE_PRODUCTION, DELAY_LOW_PRIORITY_ORDER

Rules executed: RULE-CAPACITY, RULE-MATERIAL, RULE-CRITICAL-DEADLINE, RULE-PRIORITY, RULE-UTILIZATION, RULE-DISRUPTION, RULE-COST

Recommended action: REDISTRIBUTE_PRODUCTION

Decision status: DECIDED

Total financial impact: €70.700

Avoided cost vs baseline: €26.971

Source: SYNTHETIC_DEMONSTRATION

Engine v1.0.0 · Config v1.0 · Synthetic demonstration — not BTS & SAKER production data